Casterton Railway Precinct Activation

Share Casterton Railway Precinct Activation on Facebook Share Casterton Railway Precinct Activation on Twitter Share Casterton Railway Precinct Activation on Linkedin Email Casterton Railway Precinct Activation link

Council has received federal funding from the Local Roads and Community Infrastructure Program Phase 4 for completion of works to the Casterton Railway Precinct.

These works will include:

  • Upgrades to the existing pathways
  • Inclusion of all an abilities accessible pathway from Wathen Street
  • Replacement of the picnic table and bollards
  • Repainting of the existing rotunda and removal of one section of seat for wheelchair access
  • Drainage works
  • Replacement of the equipment in the playground

Community consultation took place online and in person in Casterton in April 2025 where we showcased the plans for the precinct and asked community to select their top 5 things they loved to see in playground. We received a total of 44 submissions that helped inform the selection of the replacement playground equipment.

Works are currently underway to deliver the project. Be sure to subscribe to this project for regular updates during the phased works.

Council has received federal funding from the Local Roads and Community Infrastructure Program Phase 4 for completion of works to the Casterton Railway Precinct.

These works will include:

  • Upgrades to the existing pathways
  • Inclusion of all an abilities accessible pathway from Wathen Street
  • Replacement of the picnic table and bollards
  • Repainting of the existing rotunda and removal of one section of seat for wheelchair access
  • Drainage works
  • Replacement of the equipment in the playground

Community consultation took place online and in person in Casterton in April 2025 where we showcased the plans for the precinct and asked community to select their top 5 things they loved to see in playground. We received a total of 44 submissions that helped inform the selection of the replacement playground equipment.

Works are currently underway to deliver the project. Be sure to subscribe to this project for regular updates during the phased works.

  • Works update - 20 August 2025

    Share Works update - 20 August 2025 on Facebook Share Works update - 20 August 2025 on Twitter Share Works update - 20 August 2025 on Linkedin Email Works update - 20 August 2025 link
    supporting image

    Council is pleased to advise that demolition of the existing pathway is now complete.

    The old picnic tables, bollards, and bins have been removed, rotunda restoration is underway and new picnic tables and bollards have been ordered.

    The project is progressing through the next phase of preparing the base surface for the new asphalt pathway.

    Council appreciates the community’s continued support and looks forward to revitalising this valued public space.

  • Works are about to commence!

    Share Works are about to commence! on Facebook Share Works are about to commence! on Twitter Share Works are about to commence! on Linkedin Email Works are about to commence! link

    We’re thrilled to share that Phase 1 of the highly anticipated upgrade to the Casterton Railway Precinct is set to begin next week!

    This first stage will kick off a series of improvements designed to make the precinct more accessible, inclusive, and enjoyable for everyone. Works will include:

    • New all-abilities accessible pathway from Wathen Street

    • Replacement of picnic tables and bollards

    • Repainting of the rotunda and modified seating to support wheelchair access

    • Improved drainage infrastructure

    What’s next?
    Once Phase 1 is complete, we’ll move into Phase 2, the installation of brand-new inclusive playground equipment! This exciting addition was shaped by community input, with local voices helping to choose the features that will bring fun, accessibility, and connection to families..

    We anticipate all works will be finished by December 2025, weather permitting.

    Temporary Site Closure
    During Phase 1, the site will be closed to the public, including all walking paths. For your safety, please avoid the area while works are underway.

    Council is proud to deliver upgraded community spaces that reflect the needs and aspirations of our residents. Thank you for your patience and support as we bring this beloved precinct to life!