Cape Bridgewater Amenities project

Share Cape Bridgewater Amenities project on Facebook Share Cape Bridgewater Amenities project on Twitter Share Cape Bridgewater Amenities project on Linkedin Email Cape Bridgewater Amenities project link

The multi-million transformation of one of the Glenelg Shire’s most loved tourist attractions has taken shape. Stage 1 and 2 are now complete with the final stage about to commence that will see a refurbishment of the existing amenities building. Have your say on the refurbishment of the Cape Bridgewater Amenities refurbishment.

The Cape Bridgewater Infrastructure Masterplan was developed in 2014, following extensive community consultation and has been funded as part of the Federal Governments Local Roads and Community Infrastructure Program (LRCI). A recent review of the LRCI project delivery program was undertaken with funding and scope changes proposed to the Cape Bridgewater Amenities Upgrade. At the February 2025 Council Meeting, Council Endorsed a project funding and scope variation of the Cape Bridgewater Amenities Upgrade to provide for a facility refurbishment.

Council undertook consultation the community in early 2025 to understand what areas to prioritise as part of the refurbishment of the existing building.

Including some of the following areas:

  • Shower cubicles
  • Hot water
  • Painting
  • New fixtures and fittings
  • Changing cubicles
  • Replacement of temporary retaining fence
  • Relocation of outdoor shower

The works are currently underway. Subscribe to this project for updates.


This project connects with our Council and Wellbeing Plan 2025-2029 Year 1 Action Plan

Our Focus: Quality fit for purpose facilities places and infrastructure.

The multi-million transformation of one of the Glenelg Shire’s most loved tourist attractions has taken shape. Stage 1 and 2 are now complete with the final stage about to commence that will see a refurbishment of the existing amenities building. Have your say on the refurbishment of the Cape Bridgewater Amenities refurbishment.

The Cape Bridgewater Infrastructure Masterplan was developed in 2014, following extensive community consultation and has been funded as part of the Federal Governments Local Roads and Community Infrastructure Program (LRCI). A recent review of the LRCI project delivery program was undertaken with funding and scope changes proposed to the Cape Bridgewater Amenities Upgrade. At the February 2025 Council Meeting, Council Endorsed a project funding and scope variation of the Cape Bridgewater Amenities Upgrade to provide for a facility refurbishment.

Council undertook consultation the community in early 2025 to understand what areas to prioritise as part of the refurbishment of the existing building.

Including some of the following areas:

  • Shower cubicles
  • Hot water
  • Painting
  • New fixtures and fittings
  • Changing cubicles
  • Replacement of temporary retaining fence
  • Relocation of outdoor shower

The works are currently underway. Subscribe to this project for updates.


This project connects with our Council and Wellbeing Plan 2025-2029 Year 1 Action Plan

Our Focus: Quality fit for purpose facilities places and infrastructure.

  • Works update - 24/10/2025

    Share Works update - 24/10/2025 on Facebook Share Works update - 24/10/2025 on Twitter Share Works update - 24/10/2025 on Linkedin Email Works update - 24/10/2025 link
    supporting image

    We are pleased to share that works at Bridgewater Amenities is progressing well.

    Works completed to date:

    • External and internal painting
    • New fascia and cladding
    • Replacement of the temporary retaining fence

    Upcoming works:

    • Installation of shower cubicles
    • Installation of a hot water system servicing all internal showers
    • New fixtures and fittings

    To facilitate the works, the amenities building is temporarily closed. Temporary toilets have been provided for community use.

    We anticipate completion of works by November 2025, weather permitting.

    Council appreciates your patience as we undertake these important works and improve public infrastructure.

    Subscribe to this project via the "Stay Informed" tab to receive email updates on this project.

  • Works are underway

    Share Works are underway on Facebook Share Works are underway on Twitter Share Works are underway on Linkedin Email Works are underway link

    Upgrade to the Cape Bridgewater Public Amenities is underway!

    This marks Phase 3 of the Bridgewater Masterplan Works and will deliver a range of upgrades designed to make the amenities more functional, fresh and convenient for the community.

    Works will include:

    • Installation of shower cubicles
    • Installation of a hot water system servicing all internal showers
    • External and internal painting
    • New fixtures and fittings
    • Replacement of the temporary retaining fence

    What’s next?

    Works will begin externally, keeping the amenities building open to the public. Once external works are complete, the amenities building will be temporarily closed to allow internal upgrades to proceed. During this period, temporary toilets will be provided near the amenities for community use.

    We anticipate completion of works by November 2025, weather permitting.

    Council appreciates your patience as we undertake these important works and improve public infrastructure.

    Subscribe to this project via the "Stay Informed" tab to receive email updates on this project.