21 June 2024

The installation of the new pathway lighting is progressing well. The footings for the light poles have been poured and the installation of the conduit is almost completed. Installation of the poles has commenced at the southern end of the Foreshore (near the skate park and all abilities play space).

The next steps are installation of the lights on the poles and the wiring of the power.